Skip to main content

Project Timeline

Current Timeline

June 2020

Construction on Phase 1, the dining addition to Sharples, begins with site enabling and includes the removal of trees and plantings to the south and west of Sharples, the installation of temporary walkways, and the demolition of 5 Sharples Lane. 

June 2020

Design process begins for Phase 2, the community common space.

July 2020

Storm water, sanitary water, and electric lines are relocated, and gas lines and hydronic piping are installed

August 2020

Utility work is completed.

September 2020

Structural work and building excavation begin for the Sharples dining addition.

March 2021

Steel framing begins for the Sharples dining addition.

May 2021

Work begins on the interior and exterior of the Sharples dining addition, starting with the basement.

June 2021

Work begins on the first floor of the Sharples dining addition.

July 2021

Work begins on the second floor of the Sharples dining addition

June 2022

Construction of Phase 1, the Sharples dining addition, is complete, and transition to Phase 2 begins.

July 2022

Construction begins on Phase 2, the community commons, with the renovation of the existing Sharples building.

August 2023

Phase 2 construction is completed.